Changing MS Project to 20-hour or 30-hour week.
Posted
by Eric
on Super User
See other posts from Super User
or by Eric
Published on 2010-03-24T22:44:50Z
Indexed on
2010/03/24
22:53 UTC
Read the original article
Hit count: 156
ms-project
|calendar
I'm working on a project in MS Project and the default is a 40-hour week. I'm putting each individual task in based on a number of hours, not days. I'd like to have the whole thing set up and computing at 40-hour weeks, and then change it to 20 hours and have the project recompute. How do I do this? I think it has something to do with changing the "project calendar" but I can't quite figure it out.