Changing MS Project to 20-hour or 30-hour week.

Posted by Eric on Super User See other posts from Super User or by Eric
Published on 2010-03-24T22:44:50Z Indexed on 2010/03/24 22:53 UTC
Read the original article Hit count: 152

Filed under:
|

I'm working on a project in MS Project and the default is a 40-hour week. I'm putting each individual task in based on a number of hours, not days. I'd like to have the whole thing set up and computing at 40-hour weeks, and then change it to 20 hours and have the project recompute. How do I do this? I think it has something to do with changing the "project calendar" but I can't quite figure it out.