FogBugz - Estimate & EBS

Posted by Jeremiah on Stack Overflow See other posts from Stack Overflow or by Jeremiah
Published on 2010-04-09T16:14:10Z Indexed on 2010/04/09 16:43 UTC
Read the original article Hit count: 571

Filed under:
|
|

I have a FogBugz question regarding EBS (Evidence Based Scheduling)...

Developer A estimates Case A at X amount and Developer B ends up taking over Case A before Developer A can get started and before time has been logged against it. If Developer B agrees with the same estimate that Developer A entered, how might we transfer that same estimate to Developer B for the purpose of evidence-based scheduling?

(I want to avoid having Developer B switch the estimate to Y and then back to X)

© Stack Overflow or respective owner