SSAS Cube reprocessing fails - then succeeds if I try again

Posted by EdgarVerona on Stack Overflow See other posts from Stack Overflow or by EdgarVerona
Published on 2010-04-26T15:20:49Z Indexed on 2010/04/26 15:23 UTC
Read the original article Hit count: 392

So I'm basically brand new to the concept of BI, and I've inherited an existing ETL process that is a two step process:

1) Loads the data into a database that is only used by the cube processing 2) Starts off the SSAS cube processing against said database

It seems pretty well isolated, but occasionally (once a week, sometimes twice) it will fail with the following exception:

"Errors in the OLAP storage engine: The attribute key cannot be found"

Now the interesting thing is that:

1) The dimension having the issue is not usually the same one (i.e. there's no single dimension that consistently has this failure) 2) The source table, when I inspect it, does actually contain the attribute key that it says could not be found

And, most interestingly...

3) If I then immediately reprocess the dimensions and cubes manually through SSMS, they reprocess successfully and without incident.

In both the aforementioned job and when I reprocess them through SSMS, I am using "ProcessFull", so it should be reprocessing them completely.

Has anyone run into such an issue? I'm scratching my head about it... because if it was a genuine data integrity issue, reprocessing the cube again wouldn't fix it. What on earth could be happening? I've been tasked with finding out why this happens, but I can neither reproduce it consistently nor can I point to a data integrity problem as the root cause.

Thanks for any input you can provide!

© Stack Overflow or respective owner

Related posts about ssas

Related posts about attribute-keys