Handling inconcistent resource availability in Project 2007

Posted by Lachlan McDonald on Super User See other posts from Super User or by Lachlan McDonald
Published on 2010-06-07T03:11:11Z Indexed on 2010/06/07 3:12 UTC
Read the original article Hit count: 501

Afternoon all,

I have four resources; a project manager, and three developers. The project manager can work anywhere from 9 to 5pm each day, but only for a total of 10 hours per week. It doesn't matter when he works, as long as he isn't over-allocated 10 hours per week.

The developers on the other hand can only work up to 2 hours per day, for a total of 10 hours per week. If they work more than 2 hours in a day, they are over-allocated.

How do I best configure Project to handle this kind of scheduling requirement?

© Super User or respective owner

Related posts about microsoft-project

Related posts about microsoft-project-2007