MS Project - Schedule short duration tasks that stay within working hrs

Posted by Dave Warwick on Super User See other posts from Super User or by Dave Warwick
Published on 2011-06-28T23:43:42Z Indexed on 2011/06/29 0:24 UTC
Read the original article Hit count: 483

Filed under:

I am planning a series of tests that take a couple of hours each. However, you can not split a test so I do not want the next test to begin if there is not enough time within the specified working hours of the day to complete it. Also, I would like to begin each day with a set-up period before the actual testing can begin.

Is there a way to automatically begin each day with a setup period and have tasks that can not complete before the end of the specified work day defer starting until the next day?