How to handle estimates for programmers joining the team?
Posted
by
Jordan
on Programmers
See other posts from Programmers
or by Jordan
Published on 2012-06-19T13:57:05Z
Indexed on
2012/06/19
15:23 UTC
Read the original article
Hit count: 315
agile
|estimation
Iteration has already started, new programmer joins the team, task X has already been estimated to be 30 hours by a different developer.
What is the best practice in this situation?
- new developer runs with the given estimate (the idea being that any discrepancy will be corrected for when velocity is calculated?)
- new developer re-estimates task? (if so, what if it's significantly higher and no longer fits in the iteration?)
- throw our hands up and go back to waterfall?
- something else entirely?
© Programmers or respective owner