Webcor Builders Coordinates Construction Schedules and Mitigates Potential Delays More Efficiently with Integrated Project Management

Posted by Sylvie MacKenzie, PMP on Oracle Blogs See other posts from Oracle Blogs or by Sylvie MacKenzie, PMP
Published on Tue, 11 Sep 2012 04:00:00 +0000 Indexed on 2012/09/11 9:45 UTC
Read the original article Hit count: 293

With more than 40 years of commercial construction experience, Webcor Builders is a leading builder of distinguished, high-profile projects, including high-rise condominiums and hotels, laboratories, healthcare centers, and public works projects. Webcor is also known for its award-winning concrete, interior construction, historic restoration, and seismic renovation work. The company has completed more than 50 million square feet of projects to date.

Considering the variety and complexity of the construction projects Webcor undertakes, an integrated project management solution is critical to ensuring optimal efficiency and completing client projects on time and on budget. The company previously used a number of scheduling systems for its various building projects. These packages provided different levels of schedule detail and required schedulers, engineers, and other employees to learn multiple systems. From an IT cost and complexity perspective, the company had to manage multiple scheduling systems and pay for multiple sets of licenses.

The company looked to standardize on an enterprise project management system, and selected Oracle’s Primavera P6 Enterprise Project Portfolio Management. Webcor uses the solution’s advanced capabilities to schedule complex projects, analyze delays, model and propose multiple scenarios to demonstrate and mitigate delays and cost overruns, and process that information efficiently to deliver the scheduling precision that public and private projects require. In fact, the solution was instrumental in helping the company’s expansion into public sector projects during the recent economic downturn, and with Primavera P6 in place, it can deliver the precise schedule reporting required for large public projects.

With Primavera P6 in place, the company could deliver the precise scheduling and milestone reporting capabilities required for large public projects.

The solution is in managing the high-profile University of California – Berkeley Memorial Stadium project. Webcor was hired as construction manager and general contractor for the stadium renovation project, which is a fast-paced project located near the seismically active Hayward Fault Zone. Due to the University of California’s football schedule, meeting the Universities deadline for the coming season placed Webcor in a situation where risk awareness and early warnings of issues would be paramount. Webcor and the extended project team needed a solution that could instantly analyze alternate scenarios to mitigate potential delays; Primavera would deliver those answers.The team would also need to enable multiple stakeholders to use an internet-based platform to access the schedule from various locations, and model complicated sequencing requirements where swift decisions would be made to keep the project on track.

The schedule is an integral part of Webcor’s construction management process for the stadium project. Rather than providing the client with the industry-standard monthly update, Webcor updates the critical path method (CPM) schedule on a weekly basis. The project team also reviews the schedule and updates weekly to confirm that progress and forecasted performance are accurate.

Hired by the University for their ability to deliver in high risk environments The Webcor team was hit recently with a design supplement that could have added up to 70 days to the project. Using Oracle Primavera P6 the team sprung into action analyzing multiple “what if” scenarios to review mitigation means and methods.  Determined to make sure the Bears could take the field in the coming season the project team nearly eliminated the impact with their creative analysis in working the schedule. The total time from the issuance of the final design supplement to an agreed mitigation response was less than one week; leveraging the Oracle Primavera solution Webcor was able to deliver superior customer value

With the ability to efficiently manage projects and schedules, Webcor can ensure it completes its projects on time and on budget, as well as inform clients about what changes to plans will mean in terms of delays and additional costs.

Read the complete customer case study at : 

http://www.oracle.com/us/corporate/customers/customersearch/webcor-builders-1-primavera-ss-1639886.html