Strange Maintenance Plan SubPlans behaviour: each SP runs all the tasks of all other SP at odd times

Posted by Wentu on Server Fault See other posts from Server Fault or by Wentu
Published on 2012-09-14T14:15:18Z Indexed on 2012/09/14 15:39 UTC
Read the original article Hit count: 295

SQL Server 2005: I have a problem with scheduling a Maintenance Plan (MP) with 3 subplans (SP). SP1 is scheduled to run hourly, SP2 daily at 7.00 and SP3 on sundays at 8.00

Reading MP history I see that what happened (I know it seems crazy) is: 11: SP1 runs and executes all the tasks of SP1 SP2 and SP3 12: SP2 runs and does the same 13: SP3 runs and does the same 14: SP1 runs and does the same

From the job Activity monitor, SP1 has last run time at 14, SP2 and SP3 are never been executed. All of the SP are scheduled correctly in the Job Activity Monitor (SP2 for tomorrow at 7, SP3 for next sunday at 8)

Do you have any idea what is happening?

Thankx a lot

Wentu

© Server Fault or respective owner

Related posts about sql-server-2005

Related posts about maintenance-plan