How can you force the start and end date of a task in Microsoft Project to be on the same day?
Posted
by
Hauke P.
on Super User
See other posts from Super User
or by Hauke P.
Published on 2013-10-29T15:43:00Z
Indexed on
2013/10/29
15:59 UTC
Read the original article
Hit count: 257
microsoft-project
|microsoft-project-2013
I have a task called "Interview person A about topic X". The task's duration is set to 2 hours. The start date of the task should automatically be calculated taking dependencies and resource availabilities into account.
My question boils down to: How can I force this task to start and end on the same date?
Background: In my case, Microsoft Project sets the start date to a Friday at 5pm. As my working hours are set to 8am to 12am and 1pm to 6pm (Mon-Fri), Microsoft Project "splits up" the task at 6pm on Friday and plans to continue it at 8am on the following Monday.
However, it does not make any sense to stop the interview on a Friday and restart it on Monday. Therefore the automatic suggestion is not helpful in this case.
That's why I'm looking for a way way to force the task to start and end on the very same day. (In my example, I'd like Microsoft Project to delay the start date of the task until Monday 8am as this is the first time slot in which the task "fits in completely".)
By the way: I have lots of such cases... for that reason it would be really great if there was a solution that doesn't just deal with this single special case.)