How to write a user story specific to tasks in this case

Posted by vignesh on Programmers See other posts from Programmers or by vignesh
Published on 2014-08-18T10:32:12Z Indexed on 2014/08/18 16:44 UTC
Read the original article Hit count: 477

We have planned to take up an user story say

As a player I want to view the game map to know current standings of my team

The sprint is for two weeks. We will be able to complete only HTML in two weeks time, this user story will take 4-6 weeks to be completed as we have a shortage of content designing resources.

How can we change this user story so that HTML completion can be considered as a done for this user story and we need to take up the integration of this user story in the next sprint?

Is it possible to create two different user stories, one for HTML and other for integration, testing, bug fixing etc?