So, when we initially created our MPP schedule, I made use of indends / subordinates to break down the project by the various stages of the lifecycle, which is fine... no issues there... But now that I'm trying to publish this over to TFS display, it'll only pick up the actual "action items / sub-tasks" seeing as I have resource allocation specified. So for example I have an "Analysis" phase with a few items underneath, and "System Requirements" phase with the same items, so when I publish these to TFS, it won't display the "Parent" distinction between items, so both "Tasks" instances are being published in TFS under the exact same name... So, if I can't do this Automatically, I'll likely have edit each tasks with "Analysis - Item 1", "Analysis - item 2", "SRD - Item 1", "SRD - item 2"... is there a way to do this automatically, or will have to go the manual route??