MPXJ - get ResourceAssignment baseline values
- by patmortech
I'm trying to display the Baseline Start, Finish, Cost, and Work values for a ResourceAssignment, but cannot seem to find any methods on the ResourceAssignment object that would provide this information. Anybody know if this is possible?
I know the information is stored because I can see it in MS Project, and I can see it in the XML version of the project file. Just can't see in the API where to get access to it.