Search Results

Search found 2 results on 1 pages for 'rafik takieddin'.

Page 1/1 | 1 

  • windows 8 recovery partition

    - by Rafik Takieddin
    Recently I have bought a second hand HP Notebook from a friend. The PC still has the recovery partition not backed up yet. However, I'm thinking of resetting Windows using the new Windows 8 resetting feature. Windows warned me that all files will be deleted. Is it okay to reset Windows then backup the recovery partition in order to have a fresh backup or this can lead to losing the recovery partition and, with it, my genuine copy of Windows 8?

    Read the article

  • LUKOIL Overseas Holding Optimizes Oil Field Development Projects with Integrated Project Management

    - by Melissa Centurio Lopes
    Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4 /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-qformat:yes; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin-top:0in; mso-para-margin-right:0in; mso-para-margin-bottom:10.0pt; mso-para-margin-left:0in; line-height:115%; mso-pagination:widow-orphan; font-size:11.0pt; font-family:"Calibri","sans-serif"; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:"Times New Roman"; mso-bidi-theme-font:minor-bidi;} LUKOIL Overseas Group is a growing oil and gas company that is an integral part of the vertically integrated oil company OAO LUKOIL. It is engaged in the exploration, acquisition, integration, and efficient development of oil and gas fields outside the Russian Federation to promote transforming LUKOIL into a transnational energy company. In 2010, the company signed a 20-year development project for the giant, West Qurna 2 oil field in Iraq. Executing 10,000 to 15,000 project activities simultaneously on 14 major construction and drilling projects in Iraq for the West Qurna-2 project meant the company needed a clear picture, in real time, of dependencies between its capital construction, geologic exploration and sinking projects—required for its building infrastructure oil field development projects in Iraq. LUKOIL Overseas Holding deployed Oracle’s Primavera P6 Enterprise Project Portfolio Management to generate structured project management information and optimize planning, monitoring, and analysis of all engineering and commercial activities—such as tenders, and bulk procurement of materials and equipment—related to oil field development projects. A word from LUKOIL Overseas Holding Ltd. “Previously, we created project schedules on desktop computers and uploaded them to the project server to be merged into one big file for each project participant to access. This was not scalable, as we’ve grown and now run up to 15,000 activities in numerous projects and subprojects at any time. With Oracle’s Primavera P6 Enterprise Project Portfolio Management, we can now work concurrently on projects with many team members, enjoy absolute security, and issue new baselines for all projects and project participants once a week, with ease.” – Sergey Kotov, Head of IT and the Communication Office, LUKOIL Mid-East Ltd. Oracle Primavera Solutions: · Facilitated managing dependencies between projects by enabling the general scheduler to reschedule all projects and subprojects once a week, realigning 10,000 to 15,000 project activities that the company runs at any time · Replaced Microsoft Project and a paper-based system with a complete solution that provides structured project data · Enhanced data security by establishing project management security policies that enable only authorized project members to edit their project tasks, while enabling each project participant to view all project data that are relevant to that individual’s task · Enabled the company to monitor project progress in comparison to the projected plan, based on physical project assets to determine if each project is on track to conclude within its time and budget limitations To view the full list of solutions view here. “Oracle Gold Partner Parma Telecom was key to our successful Primavera deployment, implementing the software’s basic functionalities, such as project content, timeframes management, and cost management, in addition to performing its integration with our enterprise resource planning system and intranet portal within ten months and in accordance with budgets,” said Rafik Baynazarov, head of the master planning and control office, LUKOIL Mid-East Ltd. “ To read the full version of the customer success story, please view here.

    Read the article

1