Moving server room to another part of the building

Posted by PHLiGHT on Server Fault See other posts from Server Fault or by PHLiGHT
Published on 2011-03-09T13:25:11Z Indexed on 2011/03/09 16:12 UTC
Read the original article Hit count: 275

Filed under:
|
|

This question is a bit different than the typical we are moving our server room to an off site location or we are moving the whole office to a new building.

Management wants to add some more office space and to do so they want to move the server room to another location. The server room has Verizon smart jacks, a few servers, PBX and all the office network drops go into this room. I'm going to go over there to scout out an alternate location for the equipment because that is still TBD. This sounds like quite a pain since the Verizon equipment for our MPLS will need to be moved (never done that) and the office jacks will need to be re-run.

How do you handle the jacks? I was thinking of keeping them in the same location and having new wall plates put in with half the ports going to the current location and the other half to the new location. Or do you think that 40 drops could just be done over the weekend so the old stuff would be ripped out and replaced with the new? Currently the wiring is a mess so this could be a blessing in the long run.