Handling inconcistent resource availability in Project 2007
- by Lachlan McDonald
Afternoon all,
I have four resources; a project manager, and three developers. The project manager can work anywhere from 9 to 5pm each day, but only for a total of 10 hours per week. It doesn't matter when he works, as long as he isn't over-allocated 10 hours per week.
The developers on the other hand can only work up to 2 hours per day, for a…