Search Results

Search found 16094 results on 644 pages for 'it helpdesk team manager'.

Page 28/644 | < Previous Page | 24 25 26 27 28 29 30 31 32 33 34 35  | Next Page >

  • Xfce Power Manager on Xubuntu 13.10 doesn't work

    - by kirokko
    The problem is that its actually works, but something works with Xfce Power Manager at the same time. For example, I set that if I pressed Suspend button (on my Lenovo B560 its Fn+F2 hotkey) then system ask me what to do. But when Log out window appears, system goes to suspend. Another example is closing the lid. I set it to lock the screen via Xfce Power Manager, but system still goes to suspend. I thought that it might be laptop-mode-tools, but it's not installed. Before 13.10 I had 13.04 and everything were fine.

    Read the article

  • When using Microsoft Test Manager 2010 with SfTS, how do QA engineers know what tests they have to run?

    - by MADCookie
    We are moving our projects to TFS 2010 using the SfTS v3 (Scrum for Team System) template. We need to understand how Microsoft Test Manager is supposed to be used in this Scrum process. Specific scenario & question: The QA manager uses Test Manager to create Acceptance Test Work Items (WIs). These new WIs are created and "assigned to" him. The manager doesn't run all the tests, instead he wants to give that responsibility to his staff. How is a QA engineer supposed to know that he has tests to run? Everything says it is assigned to the manager.

    Read the article

  • Ubuntu Software Center and Update Manager fail to open

    - by Giancarlo Palmiotti
    After attempting to install Google Chrome i386 the installation failed. I then proceeded to the AMD64 to see if it was the problem but...... My computer froze and I forced shut down. Now apport has a message saying An Error occurred please run Package Manager to fix the problem E:the package google-chrome-stable needs to be reinstalled but but i cant find an archive on it) This usually means your packages have unmet dependencies. Solution anyone PS:Update manager does not work and I don't have Snyaptic. The file itself failed at the real real end and froze everything but the cursor.

    Read the article

  • Installing 12.04 through Update Manager on a XP/ubuntu dual-boot

    - by Madeline Mcormick
    I currently have a dual-boot system running XP Pro SP3 with Ubuntu 10.04 LTS. I decided to upgrade to 12.04 using the Update Manager from the network and NOT using ISO CD version. Now that I am in the middle of 12.04 installation, I have this immense fear that this upgrade from update manager on the network server may affect my Win XP OS and may render it un-bootable. I tried backing up files while its upgrading to Ubuntu but it does not recognize any external media like external HDD. What should I do?

    Read the article

  • How to implement a single instance app manager in java (CVM PhoneME)?

    - by Marcus
    Hi, I'm working on a application manager for embeded platform based on the CVM PhoneME VM. The VM is started by a C++ app which configures the CVM and then triggers the VM itself. This C++ app is called form the command line passing the main class name and the classpath of a java application. There is a main java app (lets call it Manager) which loads the app using classloaders. I want this manager to be a single instance application so it could track all running apps. In other words: The first time I start an app (app1 for instance), the VM will launch and the Manager will load the app1. In further calls to load other apps (app2, app3 and so on), the same instance of the Manager would load those apps. The manager is working fine, except for the fact that this is not a single instance. Is it possible to do what I want? I found this: http://www.knowledgesutra.com/forums/topic/59760-how-to-implement-single-instance-application-on-java/ This is almost the same I want, except for the app loading part. However, the necessary packages are not available in the CVM implementation. Thanks very much.

    Read the article

  • Agile Development

    - by James Oloo Onyango
    Alot of literature has and is being written about agile developement and its surrounding philosophies. In my quest to find the best way to express the importance of agile methodologies, i have found Robert C. Martin's "A Satire Of Two Companies" to be both the most concise and thorough! Enjoy the read! Rufus Inc Project Kick Off Your name is Bob. The date is January 3, 2001, and your head still aches from the recent millennial revelry. You are sitting in a conference room with several managers and a group of your peers. You are a project team leader. Your boss is there, and he has brought along all of his team leaders. His boss called the meeting. "We have a new project to develop," says your boss's boss. Call him BB. The points in his hair are so long that they scrape the ceiling. Your boss's points are just starting to grow, but he eagerly awaits the day when he can leave Brylcream stains on the acoustic tiles. BB describes the essence of the new market they have identified and the product they want to develop to exploit this market. "We must have this new project up and working by fourth quarter October 1," BB demands. "Nothing is of higher priority, so we are cancelling your current project." The reaction in the room is stunned silence. Months of work are simply going to be thrown away. Slowly, a murmur of objection begins to circulate around the conference table.   His points give off an evil green glow as BB meets the eyes of everyone in the room. One by one, that insidious stare reduces each attendee to quivering lumps of protoplasm. It is clear that he will brook no discussion on this matter. Once silence has been restored, BB says, "We need to begin immediately. How long will it take you to do the analysis?" You raise your hand. Your boss tries to stop you, but his spitwad misses you and you are unaware of his efforts.   "Sir, we can't tell you how long the analysis will take until we have some requirements." "The requirements document won't be ready for 3 or 4 weeks," BB says, his points vibrating with frustration. "So, pretend that you have the requirements in front of you now. How long will you require for analysis?" No one breathes. Everyone looks around to see whether anyone has some idea. "If analysis goes beyond April 1, we have a problem. Can you finish the analysis by then?" Your boss visibly gathers his courage: "We'll find a way, sir!" His points grow 3 mm, and your headache increases by two Tylenol. "Good." BB smiles. "Now, how long will it take to do the design?" "Sir," you say. Your boss visibly pales. He is clearly worried that his 3 mms are at risk. "Without an analysis, it will not be possible to tell you how long design will take." BB's expression shifts beyond austere.   "PRETEND you have the analysis already!" he says, while fixing you with his vacant, beady little eyes. "How long will it take you to do the design?" Two Tylenol are not going to cut it. Your boss, in a desperate attempt to save his new growth, babbles: "Well, sir, with only six months left to complete the project, design had better take no longer than 3 months."   "I'm glad you agree, Smithers!" BB says, beaming. Your boss relaxes. He knows his points are secure. After a while, he starts lightly humming the Brylcream jingle. BB continues, "So, analysis will be complete by April 1, design will be complete by July 1, and that gives you 3 months to implement the project. This meeting is an example of how well our new consensus and empowerment policies are working. Now, get out there and start working. I'll expect to see TQM plans and QIT assignments on my desk by next week. Oh, and don't forget that your crossfunctional team meetings and reports will be needed for next month's quality audit." "Forget the Tylenol," you think to yourself as you return to your cubicle. "I need bourbon."   Visibly excited, your boss comes over to you and says, "Gosh, what a great meeting. I think we're really going to do some world shaking with this project." You nod in agreement, too disgusted to do anything else. "Oh," your boss continues, "I almost forgot." He hands you a 30-page document. "Remember that the SEI is coming to do an evaluation next week. This is the evaluation guide. You need to read through it, memorize it, and then shred it. It tells you how to answer any questions that the SEI auditors ask you. It also tells you what parts of the building you are allowed to take them to and what parts to avoid. We are determined to be a CMM level 3 organization by June!"   You and your peers start working on the analysis of the new project. This is difficult because you have no requirements. But from the 10-minute introduction given by BB on that fateful morning, you have some idea of what the product is supposed to do.   Corporate process demands that you begin by creating a use case document. You and your team begin enumerating use cases and drawing oval and stick diagrams. Philosophical debates break out among the team members. There is disagreement as to whether certain use cases should be connected with <<extends>> or <<includes>> relationships. Competing models are created, but nobody knows how to evaluate them. The debate continues, effectively paralyzing progress.   After a week, somebody finds the iceberg.com Web site, which recommends disposing entirely of <<extends>> and <<includes>> and replacing them with <<precedes>> and <<uses>>. The documents on this Web site, authored by Don Sengroiux, describes a method known as stalwart-analysis, which claims to be a step-by-step method for translating use cases into design diagrams. More competing use case models are created using this new scheme, but again, people can't agree on how to evaluate them. The thrashing continues. More and more, the use case meetings are driven by emotion rather than by reason. If it weren't for the fact that you don't have requirements, you'd be pretty upset by the lack of progress you are making. The requirements document arrives on February 15. And then again on February 20, 25, and every week thereafter. Each new version contradicts the previous one. Clearly, the marketing folks who are writing the requirements, empowered though they might be, are not finding consensus.   At the same time, several new competing use case templates have been proposed by the various team members. Each template presents its own particularly creative way of delaying progress. The debates rage on. On March 1, Prudence Putrigence, the process proctor, succeeds in integrating all the competing use case forms and templates into a single, all-encompassing form. Just the blank form is 15 pages long. She has managed to include every field that appeared on all the competing templates. She also presents a 159- page document describing how to fill out the use case form. All current use cases must be rewritten according to the new standard.   You marvel to yourself that it now requires 15 pages of fill-in-the-blank and essay questions to answer the question: What should the system do when the user presses Return? The corporate process (authored by L. E. Ott, famed author of "Holistic Analysis: A Progressive Dialectic for Software Engineers") insists that you discover all primary use cases, 87 percent of all secondary use cases, and 36.274 percent of all tertiary use cases before you can complete analysis and enter the design phase. You have no idea what a tertiary use case is. So in an attempt to meet this requirement, you try to get your use case document reviewed by the marketing department, which you hope will know what a tertiary use case is.   Unfortunately, the marketing folks are too busy with sales support to talk to you. Indeed, since the project started, you have not been able to get a single meeting with marketing, which has provided a never-ending stream of changing and contradictory requirements documents.   While one team has been spinning endlessly on the use case document, another team has been working out the domain model. Endless variations of UML documents are pouring out of this team. Every week, the model is reworked.   The team members can't decide whether to use <<interfaces>> or <<types>> in the model. A huge disagreement has been raging on the proper syntax and application of OCL. Others on the team just got back from a 5-day class on catabolism, and have been producing incredibly detailed and arcane diagrams that nobody else can fathom.   On March 27, with one week to go before analysis is to be complete, you have produced a sea of documents and diagrams but are no closer to a cogent analysis of the problem than you were on January 3. **** And then, a miracle happens.   **** On Saturday, April 1, you check your e-mail from home. You see a memo from your boss to BB. It states unequivocally that you are done with the analysis! You phone your boss and complain. "How could you have told BB that we were done with the analysis?" "Have you looked at a calendar lately?" he responds. "It's April 1!" The irony of that date does not escape you. "But we have so much more to think about. So much more to analyze! We haven't even decided whether to use <<extends>> or <<precedes>>!" "Where is your evidence that you are not done?" inquires your boss, impatiently. "Whaaa . . . ." But he cuts you off. "Analysis can go on forever; it has to be stopped at some point. And since this is the date it was scheduled to stop, it has been stopped. Now, on Monday, I want you to gather up all existing analysis materials and put them into a public folder. Release that folder to Prudence so that she can log it in the CM system by Monday afternoon. Then get busy and start designing."   As you hang up the phone, you begin to consider the benefits of keeping a bottle of bourbon in your bottom desk drawer. They threw a party to celebrate the on-time completion of the analysis phase. BB gave a colon-stirring speech on empowerment. And your boss, another 3 mm taller, congratulated his team on the incredible show of unity and teamwork. Finally, the CIO takes the stage to tell everyone that the SEI audit went very well and to thank everyone for studying and shredding the evaluation guides that were passed out. Level 3 now seems assured and will be awarded by June. (Scuttlebutt has it that managers at the level of BB and above are to receive significant bonuses once the SEI awards level 3.)   As the weeks flow by, you and your team work on the design of the system. Of course, you find that the analysis that the design is supposedly based on is flawedno, useless; no, worse than useless. But when you tell your boss that you need to go back and work some more on the analysis to shore up its weaker sections, he simply states, "The analysis phase is over. The only allowable activity is design. Now get back to it."   So, you and your team hack the design as best you can, unsure of whether the requirements have been properly analyzed. Of course, it really doesn't matter much, since the requirements document is still thrashing with weekly revisions, and the marketing department still refuses to meet with you.     The design is a nightmare. Your boss recently misread a book named The Finish Line in which the author, Mark DeThomaso, blithely suggested that design documents should be taken down to code-level detail. "If we are going to be working at that level of detail," you ask, "why don't we simply write the code instead?" "Because then you wouldn't be designing, of course. And the only allowable activity in the design phase is design!" "Besides," he continues, "we have just purchased a companywide license for Dandelion! This tool enables 'Round the Horn Engineering!' You are to transfer all design diagrams into this tool. It will automatically generate our code for us! It will also keep the design diagrams in sync with the code!" Your boss hands you a brightly colored shrinkwrapped box containing the Dandelion distribution. You accept it numbly and shuffle off to your cubicle. Twelve hours, eight crashes, one disk reformatting, and eight shots of 151 later, you finally have the tool installed on your server. You consider the week your team will lose while attending Dandelion training. Then you smile and think, "Any week I'm not here is a good week." Design diagram after design diagram is created by your team. Dandelion makes it very difficult to draw these diagrams. There are dozens and dozens of deeply nested dialog boxes with funny text fields and check boxes that must all be filled in correctly. And then there's the problem of moving classes between packages. At first, these diagram are driven from the use cases. But the requirements are changing so often that the use cases rapidly become meaningless. Debates rage about whether VISITOR or DECORATOR design patterns should be used. One developer refuses to use VISITOR in any form, claiming that it's not a properly object-oriented construct. Someone refuses to use multiple inheritance, since it is the spawn of the devil. Review meetings rapidly degenerate into debates about the meaning of object orientation, the definition of analysis versus design, or when to use aggregation versus association. Midway through the design cycle, the marketing folks announce that they have rethought the focus of the system. Their new requirements document is completely restructured. They have eliminated several major feature areas and replaced them with feature areas that they anticipate customer surveys will show to be more appropriate. You tell your boss that these changes mean that you need to reanalyze and redesign much of the system. But he says, "The analysis phase is system. But he says, "The analysis phase is over. The only allowable activity is design. Now get back to it."   You suggest that it might be better to create a simple prototype to show to the marketing folks and even some potential customers. But your boss says, "The analysis phase is over. The only allowable activity is design. Now get back to it." Hack, hack, hack, hack. You try to create some kind of a design document that might reflect the new requirements documents. However, the revolution of the requirements has not caused them to stop thrashing. Indeed, if anything, the wild oscillations of the requirements document have only increased in frequency and amplitude.   You slog your way through them.   On June 15, the Dandelion database gets corrupted. Apparently, the corruption has been progressive. Small errors in the DB accumulated over the months into bigger and bigger errors. Eventually, the CASE tool just stopped working. Of course, the slowly encroaching corruption is present on all the backups. Calls to the Dandelion technical support line go unanswered for several days. Finally, you receive a brief e-mail from Dandelion, informing you that this is a known problem and that the solution is to purchase the new version, which they promise will be ready some time next quarter, and then reenter all the diagrams by hand.   ****   Then, on July 1 another miracle happens! You are done with the design!   Rather than go to your boss and complain, you stock your middle desk drawer with some vodka.   **** They threw a party to celebrate the on-time completion of the design phase and their graduation to CMM level 3. This time, you find BB's speech so stirring that you have to use the restroom before it begins. New banners and plaques are all over your workplace. They show pictures of eagles and mountain climbers, and they talk about teamwork and empowerment. They read better after a few scotches. That reminds you that you need to clear out your file cabinet to make room for the brandy. You and your team begin to code. But you rapidly discover that the design is lacking in some significant areas. Actually, it's lacking any significance at all. You convene a design session in one of the conference rooms to try to work through some of the nastier problems. But your boss catches you at it and disbands the meeting, saying, "The design phase is over. The only allowable activity is coding. Now get back to it."   ****   The code generated by Dandelion is really hideous. It turns out that you and your team were using association and aggregation the wrong way, after all. All the generated code has to be edited to correct these flaws. Editing this code is extremely difficult because it has been instrumented with ugly comment blocks that have special syntax that Dandelion needs in order to keep the diagrams in sync with the code. If you accidentally alter one of these comments, the diagrams will be regenerated incorrectly. It turns out that "Round the Horn Engineering" requires an awful lot of effort. The more you try to keep the code compatible with Dandelion, the more errors Dandelion generates. In the end, you give up and decide to keep the diagrams up to date manually. A second later, you decide that there's no point in keeping the diagrams up to date at all. Besides, who has time?   Your boss hires a consultant to build tools to count the number of lines of code that are being produced. He puts a big thermometer graph on the wall with the number 1,000,000 on the top. Every day, he extends the red line to show how many lines have been added. Three days after the thermometer appears on the wall, your boss stops you in the hall. "That graph isn't growing quickly enough. We need to have a million lines done by October 1." "We aren't even sh-sh-sure that the proshect will require a m-million linezh," you blather. "We have to have a million lines done by October 1," your boss reiterates. His points have grown again, and the Grecian formula he uses on them creates an aura of authority and competence. "Are you sure your comment blocks are big enough?" Then, in a flash of managerial insight, he says, "I have it! I want you to institute a new policy among the engineers. No line of code is to be longer than 20 characters. Any such line must be split into two or more preferably more. All existing code needs to be reworked to this standard. That'll get our line count up!"   You decide not to tell him that this will require two unscheduled work months. You decide not to tell him anything at all. You decide that intravenous injections of pure ethanol are the only solution. You make the appropriate arrangements. Hack, hack, hack, and hack. You and your team madly code away. By August 1, your boss, frowning at the thermometer on the wall, institutes a mandatory 50-hour workweek.   Hack, hack, hack, and hack. By September 1st, the thermometer is at 1.2 million lines and your boss asks you to write a report describing why you exceeded the coding budget by 20 percent. He institutes mandatory Saturdays and demands that the project be brought back down to a million lines. You start a campaign of remerging lines. Hack, hack, hack, and hack. Tempers are flaring; people are quitting; QA is raining trouble reports down on you. Customers are demanding installation and user manuals; salespeople are demanding advance demonstrations for special customers; the requirements document is still thrashing, the marketing folks are complaining that the product isn't anything like they specified, and the liquor store won't accept your credit card anymore. Something has to give.    On September 15, BB calls a meeting. As he enters the room, his points are emitting clouds of steam. When he speaks, the bass overtones of his carefully manicured voice cause the pit of your stomach to roll over. "The QA manager has told me that this project has less than 50 percent of the required features implemented. He has also informed me that the system crashes all the time, yields wrong results, and is hideously slow. He has also complained that he cannot keep up with the continuous train of daily releases, each more buggy than the last!" He stops for a few seconds, visibly trying to compose himself. "The QA manager estimates that, at this rate of development, we won't be able to ship the product until December!" Actually, you think it's more like March, but you don't say anything. "December!" BB roars with such derision that people duck their heads as though he were pointing an assault rifle at them. "December is absolutely out of the question. Team leaders, I want new estimates on my desk in the morning. I am hereby mandating 65-hour work weeks until this project is complete. And it better be complete by November 1."   As he leaves the conference room, he is heard to mutter: "Empowermentbah!" * * * Your boss is bald; his points are mounted on BB's wall. The fluorescent lights reflecting off his pate momentarily dazzle you. "Do you have anything to drink?" he asks. Having just finished your last bottle of Boone's Farm, you pull a bottle of Thunderbird from your bookshelf and pour it into his coffee mug. "What's it going to take to get this project done? " he asks. "We need to freeze the requirements, analyze them, design them, and then implement them," you say callously. "By November 1?" your boss exclaims incredulously. "No way! Just get back to coding the damned thing." He storms out, scratching his vacant head.   A few days later, you find that your boss has been transferred to the corporate research division. Turnover has skyrocketed. Customers, informed at the last minute that their orders cannot be fulfilled on time, have begun to cancel their orders. Marketing is re-evaluating whether this product aligns with the overall goals of the company. Memos fly, heads roll, policies change, and things are, overall, pretty grim. Finally, by March, after far too many sixty-five hour weeks, a very shaky version of the software is ready. In the field, bug-discovery rates are high, and the technical support staff are at their wits' end, trying to cope with the complaints and demands of the irate customers. Nobody is happy.   In April, BB decides to buy his way out of the problem by licensing a product produced by Rupert Industries and redistributing it. The customers are mollified, the marketing folks are smug, and you are laid off.     Rupert Industries: Project Alpha   Your name is Robert. The date is January 3, 2001. The quiet hours spent with your family this holiday have left you refreshed and ready for work. You are sitting in a conference room with your team of professionals. The manager of the division called the meeting. "We have some ideas for a new project," says the division manager. Call him Russ. He is a high-strung British chap with more energy than a fusion reactor. He is ambitious and driven but understands the value of a team. Russ describes the essence of the new market opportunity the company has identified and introduces you to Jane, the marketing manager, who is responsible for defining the products that will address it. Addressing you, Jane says, "We'd like to start defining our first product offering as soon as possible. When can you and your team meet with me?" You reply, "We'll be done with the current iteration of our project this Friday. We can spare a few hours for you between now and then. After that, we'll take a few people from the team and dedicate them to you. We'll begin hiring their replacements and the new people for your team immediately." "Great," says Russ, "but I want you to understand that it is critical that we have something to exhibit at the trade show coming up this July. If we can't be there with something significant, we'll lose the opportunity."   "I understand," you reply. "I don't yet know what it is that you have in mind, but I'm sure we can have something by July. I just can't tell you what that something will be right now. In any case, you and Jane are going to have complete control over what we developers do, so you can rest assured that by July, you'll have the most important things that can be accomplished in that time ready to exhibit."   Russ nods in satisfaction. He knows how this works. Your team has always kept him advised and allowed him to steer their development. He has the utmost confidence that your team will work on the most important things first and will produce a high-quality product.   * * *   "So, Robert," says Jane at their first meeting, "How does your team feel about being split up?" "We'll miss working with each other," you answer, "but some of us were getting pretty tired of that last project and are looking forward to a change. So, what are you people cooking up?" Jane beams. "You know how much trouble our customers currently have . . ." And she spends a half hour or so describing the problem and possible solution. "OK, wait a second" you respond. "I need to be clear about this." And so you and Jane talk about how this system might work. Some of her ideas aren't fully formed. You suggest possible solutions. She likes some of them. You continue discussing.   During the discussion, as each new topic is addressed, Jane writes user story cards. Each card represents something that the new system has to do. The cards accumulate on the table and are spread out in front of you. Both you and Jane point at them, pick them up, and make notes on them as you discuss the stories. The cards are powerful mnemonic devices that you can use to represent complex ideas that are barely formed.   At the end of the meeting, you say, "OK, I've got a general idea of what you want. I'm going to talk to the team about it. I imagine they'll want to run some experiments with various database structures and presentation formats. Next time we meet, it'll be as a group, and we'll start identifying the most important features of the system."   A week later, your nascent team meets with Jane. They spread the existing user story cards out on the table and begin to get into some of the details of the system. The meeting is very dynamic. Jane presents the stories in the order of their importance. There is much discussion about each one. The developers are concerned about keeping the stories small enough to estimate and test. So they continually ask Jane to split one story into several smaller stories. Jane is concerned that each story have a clear business value and priority, so as she splits them, she makes sure that this stays true.   The stories accumulate on the table. Jane writes them, but the developers make notes on them as needed. Nobody tries to capture everything that is said; the cards are not meant to capture everything but are simply reminders of the conversation.   As the developers become more comfortable with the stories, they begin writing estimates on them. These estimates are crude and budgetary, but they give Jane an idea of what the story will cost.   At the end of the meeting, it is clear that many more stories could be discussed. It is also clear that the most important stories have been addressed and that they represent several months worth of work. Jane closes the meeting by taking the cards with her and promising to have a proposal for the first release in the morning.   * * *   The next morning, you reconvene the meeting. Jane chooses five cards and places them on the table. "According to your estimates, these cards represent about one perfect team-week's worth of work. The last iteration of the previous project managed to get one perfect team-week done in 3 real weeks. If we can get these five stories done in 3 weeks, we'll be able to demonstrate them to Russ. That will make him feel very comfortable about our progress." Jane is pushing it. The sheepish look on her face lets you know that she knows it too. You reply, "Jane, this is a new team, working on a new project. It's a bit presumptuous to expect that our velocity will be the same as the previous team's. However, I met with the team yesterday afternoon, and we all agreed that our initial velocity should, in fact, be set to one perfectweek for every 3 real-weeks. So you've lucked out on this one." "Just remember," you continue, "that the story estimates and the story velocity are very tentative at this point. We'll learn more when we plan the iteration and even more when we implement it."   Jane looks over her glasses at you as if to say "Who's the boss around here, anyway?" and then smiles and says, "Yeah, don't worry. I know the drill by now."Jane then puts 15 more cards on the table. She says, "If we can get all these cards done by the end of March, we can turn the system over to our beta test customers. And we'll get good feedback from them."   You reply, "OK, so we've got our first iteration defined, and we have the stories for the next three iterations after that. These four iterations will make our first release."   "So," says Jane, can you really do these five stories in the next 3 weeks?" "I don't know for sure, Jane," you reply. "Let's break them down into tasks and see what we get."   So Jane, you, and your team spend the next several hours taking each of the five stories that Jane chose for the first iteration and breaking them down into small tasks. The developers quickly realize that some of the tasks can be shared between stories and that other tasks have commonalities that can probably be taken advantage of. It is clear that potential designs are popping into the developers' heads. From time to time, they form little discussion knots and scribble UML diagrams on some cards.   Soon, the whiteboard is filled with the tasks that, once completed, will implement the five stories for this iteration. You start the sign-up process by saying, "OK, let's sign up for these tasks." "I'll take the initial database generation." Says Pete. "That's what I did on the last project, and this doesn't look very different. I estimate it at two of my perfect workdays." "OK, well, then, I'll take the login screen," says Joe. "Aw, darn," says Elaine, the junior member of the team, "I've never done a GUI, and kinda wanted to try that one."   "Ah, the impatience of youth," Joe says sagely, with a wink in your direction. "You can assist me with it, young Jedi." To Jane: "I think it'll take me about three of my perfect workdays."   One by one, the developers sign up for tasks and estimate them in terms of their own perfect workdays. Both you and Jane know that it is best to let the developers volunteer for tasks than to assign the tasks to them. You also know full well that you daren't challenge any of the developers' estimates. You know these people, and you trust them. You know that they are going to do the very best they can.   The developers know that they can't sign up for more perfect workdays than they finished in the last iteration they worked on. Once each developer has filled his or her schedule for the iteration, they stop signing up for tasks.   Eventually, all the developers have stopped signing up for tasks. But, of course, tasks are still left on the board.   "I was worried that that might happen," you say, "OK, there's only one thing to do, Jane. We've got too much to do in this iteration. What stories or tasks can we remove?" Jane sighs. She knows that this is the only option. Working overtime at the beginning of a project is insane, and projects where she's tried it have not fared well.   So Jane starts to remove the least-important functionality. "Well, we really don't need the login screen just yet. We can simply start the system in the logged-in state." "Rats!" cries Elaine. "I really wanted to do that." "Patience, grasshopper." says Joe. "Those who wait for the bees to leave the hive will not have lips too swollen to relish the honey." Elaine looks confused. Everyone looks confused. "So . . .," Jane continues, "I think we can also do away with . . ." And so, bit by bit, the list of tasks shrinks. Developers who lose a task sign up for one of the remaining ones.   The negotiation is not painless. Several times, Jane exhibits obvious frustration and impatience. Once, when tensions are especially high, Elaine volunteers, "I'll work extra hard to make up some of the missing time." You are about to correct her when, fortunately, Joe looks her in the eye and says, "When once you proceed down the dark path, forever will it dominate your destiny."   In the end, an iteration acceptable to Jane is reached. It's not what Jane wanted. Indeed, it is significantly less. But it's something the team feels that can be achieved in the next 3 weeks.   And, after all, it still addresses the most important things that Jane wanted in the iteration. "So, Jane," you say when things had quieted down a bit, "when can we expect acceptance tests from you?" Jane sighs. This is the other side of the coin. For every story the development team implements,   Jane must supply a suite of acceptance tests that prove that it works. And the team needs these long before the end of the iteration, since they will certainly point out differences in the way Jane and the developers imagine the system's behaviour.   "I'll get you some example test scripts today," Jane promises. "I'll add to them every day after that. You'll have the entire suite by the middle of the iteration."   * * *   The iteration begins on Monday morning with a flurry of Class, Responsibilities, Collaborators sessions. By midmorning, all the developers have assembled into pairs and are rapidly coding away. "And now, my young apprentice," Joe says to Elaine, "you shall learn the mysteries of test-first design!"   "Wow, that sounds pretty rad," Elaine replies. "How do you do it?" Joe beams. It's clear that he has been anticipating this moment. "OK, what does the code do right now?" "Huh?" replied Elaine, "It doesn't do anything at all; there is no code."   "So, consider our task; can you think of something the code should do?" "Sure," Elaine said with youthful assurance, "First, it should connect to the database." "And thereupon, what must needs be required to connecteth the database?" "You sure talk weird," laughed Elaine. "I think we'd have to get the database object from some registry and call the Connect() method. "Ah, astute young wizard. Thou perceives correctly that we requireth an object within which we can cacheth the database object." "Is 'cacheth' really a word?" "It is when I say it! So, what test can we write that we know the database registry should pass?" Elaine sighs. She knows she'll just have to play along. "We should be able to create a database object and pass it to the registry in a Store() method. And then we should be able to pull it out of the registry with a Get() method and make sure it's the same object." "Oh, well said, my prepubescent sprite!" "Hay!" "So, now, let's write a test function that proves your case." "But shouldn't we write the database object and registry object first?" "Ah, you've much to learn, my young impatient one. Just write the test first." "But it won't even compile!" "Are you sure? What if it did?" "Uh . . ." "Just write the test, Elaine. Trust me." And so Joe, Elaine, and all the other developers began to code their tasks, one test case at a time. The room in which they worked was abuzz with the conversations between the pairs. The murmur was punctuated by an occasional high five when a pair managed to finish a task or a difficult test case.   As development proceeded, the developers changed partners once or twice a day. Each developer got to see what all the others were doing, and so knowledge of the code spread generally throughout the team.   Whenever a pair finished something significant whether a whole task or simply an important part of a task they integrated what they had with the rest of the system. Thus, the code base grew daily, and integration difficulties were minimized.   The developers communicated with Jane on a daily basis. They'd go to her whenever they had a question about the functionality of the system or the interpretation of an acceptance test case.   Jane, good as her word, supplied the team with a steady stream of acceptance test scripts. The team read these carefully and thereby gained a much better understanding of what Jane expected the system to do. By the beginning of the second week, there was enough functionality to demonstrate to Jane. She watched eagerly as the demonstration passed test case after test case. "This is really cool," Jane said as the demonstration finally ended. "But this doesn't seem like one-third of the tasks. Is your velocity slower than anticipated?"   You grimace. You'd been waiting for a good time to mention this to Jane but now she was forcing the issue. "Yes, unfortunately, we are going more slowly than we had expected. The new application server we are using is turning out to be a pain to configure. Also, it takes forever to reboot, and we have to reboot it whenever we make even the slightest change to its configuration."   Jane eyes you with suspicion. The stress of last Monday's negotiations had still not entirely dissipated. She says, "And what does this mean to our schedule? We can't slip it again, we just can't. Russ will have a fit! He'll haul us all into the woodshed and ream us some new ones."   You look Jane right in the eyes. There's no pleasant way to give someone news like this. So you just blurt out, "Look, if things keep going like they're going, we're not going to be done with everything by next Friday. Now it's possible that we'll figure out a way to go faster. But, frankly, I wouldn't depend on that. You should start thinking about one or two tasks that could be removed from the iteration without ruining the demonstration for Russ. Come hell or high water, we are going to give that demonstration on Friday, and I don't think you want us to choose which tasks to omit."   "Aw forchrisakes!" Jane barely manages to stifle yelling that last word as she stalks away, shaking her head. Not for the first time, you say to yourself, "Nobody ever promised me project management would be easy." You are pretty sure it won't be the last time, either.   Actually, things went a bit better than you had hoped. The team did, in fact, have to drop one task from the iteration, but Jane had chosen wisely, and the demonstration for Russ went without a hitch. Russ was not impressed with the progress, but neither was he dismayed. He simply said, "This is pretty good. But remember, we have to be able to demonstrate this system at the trade show in July, and at this rate, it doesn't look like you'll have all that much to show." Jane, whose attitude had improved dramatically with the completion of the iteration, responded to Russ by saying, "Russ, this team is working hard, and well. When July comes around, I am confident that we'll have something significant to demonstrate. It won't be everything, and some of it may be smoke and mirrors, but we'll have something."   Painful though the last iteration was, it had calibrated your velocity numbers. The next iteration went much better. Not because your team got more done than in the last iteration but simply because the team didn't have to remove any tasks or stories in the middle of the iteration.   By the start of the fourth iteration, a natural rhythm has been established. Jane, you, and the team know exactly what to expect from one another. The team is running hard, but the pace is sustainable. You are confident that the team can keep up this pace for a year or more.   The number of surprises in the schedule diminishes to near zero; however, the number of surprises in the requirements does not. Jane and Russ frequently look over the growing system and make recommendations or changes to the existing functionality. But all parties realize that these changes take time and must be scheduled. So the changes do not cause anyone's expectations to be violated. In March, there is a major demonstration of the system to the board of directors. The system is very limited and is not yet in a form good enough to take to the trade show, but progress is steady, and the board is reasonably impressed.   The second release goes even more smoothly than the first. By now, the team has figured out a way to automate Jane's acceptance test scripts. The team has also refactored the design of the system to the point that it is really easy to add new features and change old ones. The second release was done by the end of June and was taken to the trade show. It had less in it than Jane and Russ would have liked, but it did demonstrate the most important features of the system. Although customers at the trade show noticed that certain features were missing, they were very impressed overall. You, Russ, and Jane all returned from the trade show with smiles on your faces. You all felt as though this project was a winner.   Indeed, many months later, you are contacted by Rufus Inc. That company had been working on a system like this for its internal operations. Rufus has canceled the development of that system after a death-march project and is negotiating to license your technology for its environment.   Indeed, things are looking up!

    Read the article

  • Implementing Service Level Agreements in Enterprise Manager 12c for Oracle Packaged Applications

    - by Anand Akela
    Contributed by Eunjoo Lee, Product Manager, Oracle Enterprise Manager. Service Level Management, or SLM, is a key tool in the proactive management of any Oracle Packaged Application (e.g., E-Business Suite, Siebel, PeopleSoft, JD Edwards E1, Fusion Apps, etc.). The benefits of SLM are that administrators can utilize representative Application transactions, which are constantly and automatically running behind the scenes, to verify that all of the key application and technology components of an Application are available and performing to expectations. A single transaction can verify the availability and performance of the underlying Application Tech Stack in a much more efficient manner than by monitoring the same underlying targets individually. In this article, we’ll be demonstrating SLM using Siebel Applications, but the same tools and processes apply to any of the Package Applications mentioned above. In this demonstration, we will log into the Siebel Application, navigate to the Contacts View, update a contact phone record, and then log-out. This transaction exposes availability and performance metrics of multiple Siebel Servers, multiple Components and Component Groups, and the Siebel Database - in a single unified manner. We can then monitor and manage these transactions like any other target in EM 12c, including placing pro-active alerts on them if the transaction is either unavailable or is not performing to required levels. The first step in the SLM process is recording the Siebel transaction. The following screenwatch demonstrates how to record Siebel transaction using an EM tool called “OpenScript”. A completed recording is called a “Synthetic Transaction”. The second step in the SLM process is uploading the Synthetic Transaction into EM 12c, and creating Generic Service Tests. We can create a Generic Service Test to execute our synthetic transactions at regular intervals to evaluate the performance of various business flows. As these transactions are running periodically, it is possible to monitor the performance of the Siebel Application by evaluating the performance of the synthetic transactions. The process of creating a Generic Service Test is detailed in the next screenwatch. EM 12c provides a guided workflow for all of the key creation steps, including configuring the Service Test, uploading of the Synthetic Test, determining the frequency of the Service Test, establishing beacons, and selecting performance and usage metrics, just to name a few. The third and final step in the SLM process is the creation of Service Level Agreements (SLA). Service Level Agreements allow Administrators to utilize the previously created Service Tests to specify expected service levels for Application availability, performance, and usage. SLAs can be created for different time periods and for different Service Tests. This last screenwatch demonstrates the process of creating an SLA, as well as highlights the Dashboards and Reports that Administrators can use to monitor Service Test results. Hopefully, this article provides you with a good start point for creating Service Level Agreements for your E-Business Suite, Siebel, PeopleSoft, JD Edwards E1, or Fusion Applications. Enterprise Manager Cloud Control 12c, with the Application Management Suites, represents a quick and easy way to implement Service Level Management capabilities at customer sites. Stay Connected: Twitter |  Face book |  You Tube |  Linked in |  Google+ |  Newsletter

    Read the article

  • How to resolve the "Failed to download repository" error?

    - by jojo
    I've tried to update but then I got this error Here's the error information in that box: W:GPG error: http://extras.ubuntu.com precise Release: The following signatures were invalid: BADSIG 16126D3A3E5C1192 Ubuntu Extras Archive Automatic Signing Key <[email protected]>, W:Failed to fetch http://ppa.launchpad.net/unity-team/hud/ubuntu/dists/precise/main/source/Sources 404 Not Found, W:Failed to fetch http://ppa.launchpad.net/unity-team/hud/ubuntu/dists/precise/main/binary-i386/Packages 404 Not Found, E:Some index files failed to download. They have been ignored, or old ones used instead. And my Internet connection is working fine. After trying $ sudo apt-get install ppa-purge Reading package lists... Done Building dependency tree Reading state information... Done ppa-purge is already the newest version. The following packages were automatically installed and are no longer required: language-pack-zh-hans language-pack-kde-en language-pack-kde-zh-hans language-pack-kde-en-base kde-l10n-engb kde-l10n-zhcn language-pack-zh-hans-base firefox-locale-zh-hans language-pack-kde-zh-hans-base Use 'apt-get autoremove' to remove them. 0 upgraded, 0 newly installed, 0 to remove and 0 not upgraded. $ sudo ppa-purge ppa:unity-team/hud Updating packages lists W: GPG error: http://extras.ubuntu.com precise Release: The following signatures were invalid: BADSIG 16126D3A3E5C1192 Ubuntu Extras Archive Automatic Signing Key <[email protected]> W: Failed to fetch http://ppa.launchpad.net/unity-team/hud/ubuntu/dists/precise/main/source/Sources 404 Not Found W: Failed to fetch http://ppa.launchpad.net/unity-team/hud/ubuntu/dists/precise/main/binary-i386/Packages 404 Not Found E: Some index files failed to download. They have been ignored, or old ones used instead. Warning: apt-get update failed for some reason PPA to be removed: unity-team hud Warning: Could not find package list for PPA: unity-team hud I've tried $ sudo apt-key adv --recv-keys --keyserver keyserver.ubuntu.com 16126D3A3E5C1192 Executing: gpg --ignore-time-conflict --no-options --no-default-keyring --secret-keyring /tmp/tmp.v6Ucus0B10 --trustdb-name /etc/apt/trustdb.gpg --keyring /etc/apt/trusted.gpg --primary-keyring /etc/apt/trusted.gpg --recv-keys --keyserver keyserver.ubuntu.com 16126D3A3E5C1192 gpg: requesting key 3E5C1192 from hkp server keyserver.ubuntu.com gpg: key 3E5C1192: "Ubuntu Extras Archive Automatic Signing Key <[email protected]>" not changed gpg: Total number processed: 1 gpg: unchanged: 1 And then started the same procedure but of no use.

    Read the article

  • Is it OK to have a team with same abilities but different skill levels?

    - by A. Karimi
    I believe that in an ideal team, members should have different but complementary abilities. But is that true about software development teams? As an example we are a small team of 5. We almost have the same abilities and interests but with different levels of skills. Regarding such situation I think we don't cover our teammates' weaknesses. Is there any pattern to follow to manage and improve such team? Should I setup a team with different abilities and interests to maximize the performance and productivity? -- EDIT -- Our current team has a specific lifetime. We work together in a per-project manner. In another word we may change the team arrangement for each project depending on the project and developers situation. Actually we've provided a sort of floating situation. In short, we are a network of developers rather than a fixed-size development team.

    Read the article

  • Any way to release focus on a KVM guest in virt-manager without having to click Ctrl_L + Alt_L?

    - by slm
    Is there a way to move my mouse in and out of a KVM guest in virt-manager without having to click to gain focus of the window and release focus by pressing Ctrl_L + Alt_L? EDIT #1 The guest VM is Win2008R2. I've tried this on a CentOS 5, 6, and Fedora 14 box running various versions of virt-manager and KVM and they all exhibit this behavior. EDIT #2 I just tried the solution recommended by @tpow and that appears to be the issue. Manually adding a tablet input device resolves the problem and I can now move the mouse in and out of the KVM guest without having to gain focus first.

    Read the article

  • Unable to access ubuntu through windows boot manager

    - by Arvind
    I am having an ASUS K55VM....it came with DOS....to this Windows 7 was installed...now i am planned to add another OS ie Ubuntu...my computer had 4 partitions of 240GB 230GB 230GB and 230GB....i changed this to 5 parts....243GB 230GB 230GB 150GB and an 80GB...i installed Ubuntu 12.04 to the 80GB partition through a USB flash drive....it installed fine...however the problem is during the Boot option in Windows Boot manager when i choose Ubuntu...this what is displayed... Windows failed to start. A recent hardware or software change might be the cause. To fix the problem: 1.Insert your Windows installation disc and restart your computer. 2.Choose your language settings, and then click "Next." 3.Click "Repair your computer." If you do not have this disc, contact your system administrator or computer manufacturer for assistance. File: \ubuntu\winboot\wubildr.mbr Status: 0xc000000e Info: The selected entry could not be loaded because the application is missing or corrupt. I tried to change the boot option for the OS and made Ubuntu as my first option....It worked...however windows 7 does not show up in GRUB....in this fear i did the following: Restarted my pc changed boot option 1 to windows. Formatted the drive to which Ubuntu was installed(80GB one)through windows. Restarted again. The problem persists....Windows boot manager shows Ubuntu still and when i choose this it gives two lines one like: grub rescue....but my windows 7 is working perfectly fine. Now want a solution to remove Ubuntu from the windows boot option and reinstall completely...

    Read the article

  • Accessing host LVM partition from Windows XP through Virt.manager 0.8.5 / Qemu / KVM

    - by Nico de Smidt
    Hi, requested use case is having a Windows XP SP3 guest running in 64bit Ubuntu. (Linux pcs 2.6.35-22-server #35-Ubuntu SMP Sat Oct 16 22:02:33 UTC 2010 x86_64 GNU/Linux) I want this guest to access an LVM LV on the Ubuntu disk. I've setup the following LVM config: --- Logical volume --- LV Name /dev/storage/sdc1 VG Name storage LV UUID Zg5IMC-OlqB-prL5-fgg4-3A9A-OgKP-oZ0QkJ LV Write Access read/write LV Status available # open 0 LV Size 1.01 GiB Current LE 259 Segments 1 Allocation inherit Read ahead sectors auto - currently set to 256 Block device 251:3 -- 1) I've setup a storage pool for /dev/storage 2) I've mkfs.vfat /dev/storage/sdc1 3) and made a virtual IDE disk in the virt-manager setup for the guest. Target device: IDE Disk 2 Source path: /dev/storage/sdc1 -- Now when running XP (guest) Windows sees a new disk in Disk Manager and want's to install a partition on it, since it believes the drive is empty. After formatting from within Windows I can put data on the new disk volume. -- Back in Ubuntu however I cannot access this this any more since it created a partition within an LVM Logical Volume. Running fdisk -l shows the following: root@pcs:/media# fdisk -l /dev/storage/sdc1 Disk /dev/storage/sdc1: 1086 MB, 1086324736 bytes 32 heads, 63 sectors/track, 1052 cylinders Units = cylinders of 2016 * 512 = 1032192 bytes Sector size (logical/physical): 512 bytes / 512 bytes I/O size (minimum/optimal): 512 bytes / 512 bytes Disk identifier: 0x8d72e4f4 Device Boot Start End Blocks Id System /dev/storage/sdc1p1 1 1050 1058368+ c W95 FAT32 (LBA) -- which seems fine to me, but when trying to mount /dev/storage/sdc1p1 I get the following error: mount /dev/storage/sdc1p1 /media/xp mount: special device /dev/storage/sdc1p1 does not exist which makes sense since in lvdisplay sdc1p1 does not exist Main question: I want to mount the vfat partition in both Ubuntu and XP What am I missing here????? regards, and thanks for your consideration. Nico

    Read the article

  • Configuration Manager Setting Causing Error PRJ0019

    - by Jeff Paterno
    Recently I ran into an issue with a project failing to build on an automated build server using CruiseControl. When I looked into the build log I saw that the Post-Build project was failing with the error message: "error PRJ0019: A tool returned an error code from "Performing Post-Build Event..." This was most frustrating especially since the solution was building without issue on my local development environment. The Post-Build project was a C++ project that basically called several batch files to unregister/register assemblies, copy resources and supporting files, and place other dependencies in the GAC. I decided to run each of the batch files manually to see if that would provide more information as to why this project was failing. This lead me to determine that the batch file that was placing assemblies in the GAC was the culprit and that it was failing to find a particular assembly. The missing assembly was the output of another project. The project that was not producing the expected output was another C++ project that called a batch file. This batch process was actually embedding resource files into an assembly and then copying the assembly to the expected location. The real confusion started when I looked back into my Subversion log and noted that nothing had changed in this project in more than 2 months! It was almost as if the project had stopped building altogether. But what would cause that?! The Configuration Manager, obviously! Checking the solution's Configuration Manager settings, I found that the project that was not producing any output was in fact not selected to be part of the build process when the "Any CPU" platform was selected. This was the problem! I had recently updated the CruiseControl configurations to force the solution to be built targeting the platform "Any CPU". As a result, the project that was at the root of the problem was not configured to be built and the post-build process was failing when it couldn't find what it needed.

    Read the article

  • Daten versionieren mit Oracle Database Workspace Manager

    - by Heinz-Wilhelm Fabry (DBA Community)
    Wie können extrem lange Transaktionen durchgeführt werden, also Transaktionen, die Datensätze über Stunden oder Tage exklusiv sperren, ohne dass diese langen Transaktionen 'normale' Transaktionen auf diesen Datensätzen behindern? Solche langen Transakionen sind zum Beispiel im Spatial Umfeld keine Seltenheit. Wie können unterschiedliche historische Zustände von Produktionsdaten online zeitlich unbegrenzt vorgehalten werden? Die UNDO Daten, die das gesamte Änderungsvolumen einer Datenbank vorhalten, gewährleisten in der Regel nur einen zeitlich sehr limitierten Zugriff auf 'ältere' Daten. Und die Technologie der database archives, auch bekannt unter dem Namen Total Recall, erlaubt einerseits keine Änderungen an den älteren Daten und steht andererseits ausschließlich in der Enterprise Edition der Datenbank zur Verfügung. Wie kann man die aktuellsten Produktionsdaten für WHAT-IF-Analysen verändern und währenddessen andere Benutzer ungestört auf den Originaldaten weiterarbeiten lassen? Ein SET TRANSACTION READ ONLY erlaubt keinerlei Änderungen und ist ebenfalls begrenzt auf die 'Reichweite' der UNDO Informationen. Zwar könnte man für derartige Analysen eine Datenbankkopie aus dem Backup aufbauen oder eine Standby Lösung implementieren, aber das ist doch eher aufwändig. Es gibt eine verblüffend einfache Antwort auf diese scheinbar komplizierten Fragen. Sie heisst Oracle Database Workspace Manager oder kurz Workspace Manager (WM). Der WM ist ein Feature der Datenbank seit Oracle9i, das sowohl in der Standard als auch in der Enterprise Edition zur Verfügung steht. Anders als in den ersten Versionen ist er längst auch Bestandteil jeder Installation. Um so erstaunlicher ist es, dass so wenige Kunden ihn kennen. Dieser Tipp soll dazu beitragen, das zu ändern.

    Read the article

  • Simple Introduction to using the Enterprise Manager SOA/BPM Facade API by Jaideep Ganguli

    - by JuergenKress
    There may be times when you need to expose just a small section of what is displayed in the Enterprise Manager console for SOA/BPM (EM console). A simple example can be where stakeholders on the systems integration or customer teams want to monitor a dashboard of statistics on how many instances of a composite have been created and how many have faulted. You can see this in the EM, as shown below Some of these stakeholders may not have knowledge of  EM console and they just want a quick view into the statistics, without having to navigate EM. This post describes how to use the Oracle Fusion Middleware Infrastructure Management Java API  for Oracle SOA Suite (also called the Facade API)  to build a custom ADF page to display this information. If you want a quick introduction in using the Facade API, this post is for you. Read the complete article here. SOA & BPM Partner Community For regular information on Oracle SOA Suite become a member in the SOA & BPM Partner Community for registration please visit www.oracle.com/goto/emea/soa (OPN account required) If you need support with your account please contact the Oracle Partner Business Center. Blog Twitter LinkedIn Facebook Wiki Technorati Tags: Enterprise Manager,SOA Community,Oracle SOA,Oracle BPM,Community,OPN,Jürgen Kress

    Read the article

  • How does your team work together in a remote setup?

    - by Carl Rosenberger
    Hi, we are a distributed team working on the object database db4o. The way we work: We try to program in pairs only. We use Skype and VNC or SharedView to connect and work together. In our online Tuesday meeting every week (usually about 1 hour) we talk about the tasks done last week we create new pairs for the next week with a random generator so knowledge and friendship distribute evenly we set the priority for any new tasks or bugs that have come in each team picks the tasks it likes to do from the highest prioritized ones. From Tuesday to Wednesday we estimate tasks. We have a unit of work we call "Ideal Developer Session" (IDS), maybe 2 or 3 hours of working together as a pair. It's not perfectly well defined (because we know estimation always is inaccurate) but from our past shared experience we have a common sense of what an IDS is. If we can't estimate a task because it feels too long for a week we break it down into estimatable smaller tasks. During a short meeting on Wednesday we commit to a workload we feel is well doable in a week. We commit to complete. If a team runs out of committed tasks during the week, it can pick new ones from the prioritized queue we have in Jira. When we started working this way, some of us found that remote pair programming takes a lot of energy because you are so focussed. If you pair program for more than 5 or 6 hours per day, you get drained. On the other hand working like this has turned out to be very efficient. The knowledge about our codebase is evenly distributed and we have really learnt lots from eachother. I would be very interested to hear about the experiences from other teams working in a similar way. Things like: How often do you meet? Have you tried different sprint lengths (one week, two week, longer) ? Which tools do you use? Which issue tracker do you use? What do you do about time zone differences? How does it work for you to integrate new people into the team? How many hours do you usually work per week? How does your management interact with the way you are working? Do you get put on a waterfall with hard deadlines? What's your unit of work? What is your normal velocity? (units of work done per week) Programming work should be fun and for us it usually is great fun. I would be happy about any new ideas how to make it even more fun and/or more efficient.

    Read the article

  • Book &ldquo;Team Foundation Server 2012 Starter&rdquo; published!

    - by Jakob Ehn
    During the summer and fall this year, me and my colleague Terje Sandstrøm has worked together on a book project that has now finally hit the stores! The title of the book is Team Foundation Server 2012 Starter and is published by Packt Publishing. You can find it at http://www.packtpub.com/team-foundation-server-2012-starter/book or from Amazon http://www.amazon.com/dp/1849688389                          The book is part of a concept that Packt have with starter-books, intended for people new to Team Foundation Server 2012 and who want a quick guideline to get it up and working. It covers the fundamentals, from installing and configuring it, and how to use it with source control, work items and builds. It is done as a step-by-step guide, but also includes best practices advice in the different areas. It covers the use of both the on-premises and the TFS Services version. It also has a list of links and references in the end to the most relevant Visual Studio 2012 ALM sites. Our good friend and fellow ALM MVP Mathias Olausson have done the review of the book, thanks again Mathias! We hope the book fills the gap between the different online guide sites and the more advanced books that are out. Check it out and please let us know what you think of the book! Book Description Your quick start guide to TFS 2012, top features, and best practices with hands on examples Overview Install TFS 2012 from scratch Get up and running with your first project Streamline release cycles for maximum productivity In Detail Team Foundation Server 2012 is Microsoft's leading ALM tool, integrating source control, work item and process handling, build automation, and testing. This practical "Team Foundation Server 2012 Starter Guide" will provide you with clear step-by-step exercises covering all major aspects of the product. This is essential reading for anyone wishing to set up, organize, and use TFS server. This hands-on guide looks at the top features in Team Foundation Server 2012, starting with a quick installation guide and then moving into using it for your software development projects. Manage your team projects with Team Explorer, one of the many new features for 2012. Covering all the main features in source control to help you work more efficiently, including tools for branching and merging, we will delve into the Agile Planning Tools for planning your product and sprint backlogs. Learn to set up build automation, allowing your team to become faster, more streamlined, and ultimately more productive with this "Team Foundation Server 2012 Starter Guide". What you will learn from this book Install TFS 2012 on premise Access TFS Services in the cloud Quickly get started with a new project with product backlogs, source control, and build automation Work efficiently with source control using the top features Understand how the tools for branching and merging in TFS 2012 help you isolate work and teams Learn about the existing process templates, such as Visual Studio Scrum 2.0 Manage your product and sprint backlogs using the Agile planning tools Approach This Starter guide is a short, sharp introduction to Team Foundation Server 2012, covering everything you need to get up and running. Who this book is written for If you are a developer, project lead, tester, or IT administrator working with Team Foundation Server 2012 this guide will get you up to speed quickly and with minimal effort.

    Read the article

  • Oracle Enterprise Manager Cloud Control 12c Release 2 (12.1.0.2) is Available Now !

    - by Anand Akela
    Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4 /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-qformat:yes; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin:0in; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Times New Roman","serif";} Oracle today announced the availability of Oracle Enterprise Manager Cloud Control 12c Release 2 (12.1.0.2). It is now available for download on OTN on ALL platforms. This is the first major release since the launch of Enterprise Manager 12c in October of 2011. This is the first time when Enterprise Manager release is available on all platforms simultaneously. This is primarily a stability release which incorporates many of issues and feedback reported by early adopters. In addition, this release contains many new features and enhancements in areas across the board. New Capabilities and Features Enhanced management capabilities for enterprise private clouds: Introduces new capabilities to allow customers to build and manage a Java Platform-as-a-Service (PaaS) cloud based on Oracle Weblogic Server. The new capabilities include guided set up of PaaS Cloud, self-service provisioning, automatic scale out and metering and chargeback. Enhanced lifecycle management capabilities for Oracle WebLogic Server environments: Combining in-context multiple domain, patching and configuration file synchronizations. Integrated Hardware-Software management for Oracle Exalogic Elastic Cloud through features such as rack schematics visualization and integrated monitoring of all hardware and software components. The latest management capabilities for business-critical applications include: Business Application Management: A new Business Application (BA) target type and dashboard with flexible definitions provides a logical view of an application’s business transactions, end-user experiences and the cloud infrastructure the monitored application is running on. Enhanced User Experience Reporting: Oracle Real User Experience Insight has been enhanced to provide reporting capabilities on client-side issues for applications running in the cloud and has been more tightly coupled with Oracle Business Transaction Management to help ensure that real-time user experience and transaction tracing data is provided to users in context. Several key improvements address ease of administration, reporting and extensibility for massively scalable cloud environments including dynamic groups, self-updateable monitoring templates, bulk operations against many events, etc. New and Revised Plug-Ins: Several plug-Ins have been updated as a part of this release resulting in either new versions or revisions. Revised plug-ins contain only bug-fixes and while new plug-ins incorporate both bug fixes as well as new functionality. Plug-In Name Version Enterprise Manager for Oracle Database 12.1.0.2 (revision) Enterprise Manager for Oracle Fusion Middleware 12.1.0.3 (new) Enterprise Manager for Chargeback and Capacity Planning 12.1.0.3 (new) Enterprise Manager for Oracle Fusion Applications 12.1.0.3 (new) Enterprise Manager for Oracle Virtualization 12.1.0.3 (new) Enterprise Manager for Oracle Exadata 12.1.0.3 (new) Enterprise Manager for Oracle Cloud 12.1.0.4 (new) Installation and Upgrade: All major platforms have been released simultaneously (Linux 32 / 64 bit, Solaris (SPARC), Solaris x86-64, IBM AIX 64-bit, and Windows x86-64 (64-bit) ) Enterprise Manager 12.1.0.2 is a complete release that includes both the EM OMS and Agent versions of 12.1.0.2. Installation options available with EM 12.1.0.2: User can do fresh Install or an upgrade from versions EM 10.2.0.5, 11.1, or 12.1.0.2 ( Bundle Patch 1 not mandatory). Upgrading to EM 12.1.0.2 from EM 12.1.0.1 is not a patch application (similar to Bundle Patch 1) but is achieved through a 1-system upgrade. Documentation: Oracle Enterprise Manager Cloud Control Introduction Document provides a broad overview of capabilities and highlights"What's New" in EM 12.1.0.2. All updated Oracle Enterprise Manager documentation can be found on OTN Upgrade Guide Please feel free to ask questions related to the new Oracle Enterprise Manager Cloud Control 12c Release 2 (12.1.0.2) at the Oracle Enterprise Manager Forum . You could also share your feedback at twitter  using hash tag #em12c or at Facebook . Stay Connected: Twitter |  Face book |  You Tube |  Linked in |  Newsletter

    Read the article

  • Lesi, from Graduate Trainee to Territory Manager

    - by Maria Sandu
    Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4 It’s the final year, University is now coming to an end. A new chapter now awaits my arrival. This part of my life is called “Looking for a Job”. With no form of experience whatsoever, getting a job at a well renowned IT company is something that every IT student dreams about. CV: v, Application form: v, interviews: v. Acceptance Call, “Lesi I’m pleased to inform you that you have been accepted to be part of the Oracle Graduate Program for 2012”. Life would never again be the same. Being Part of the Graduate Program Going into the Graduate program, I felt like a baby seeing candy for the first time. The Program gave me the platform to not only break in to the workplace but also to help launch my career. Over the next 3 months, I went through various trainings / workshops / events / coaching / mentorship sessions. Like a construction worker building a solid foundation for a beautifully designed architecture, a clear path to build my career was set. With training out the way, it was now time to start working closely with my team. For the rest of the year, it was all about selling. Sales, Pipeline, Forecasting and numbers soon became the common words in my career. As the saying goes, “once a sales man, always a sales man”. There was no turning back now, a career in sales was the new hustle in my life. I worked closely with my mentor & coach (Ibrahim) who was heading up Zambia and Malawi. This was to be one of my best moments in the program as I started engaging with customers and getting some hands on experience in the field. By the end of the program all the experience, hard work, training and resources came in handy as I was now ready and fully groomed to be a sales rep. Life after the Graduate Program I’m proud to say that now I’m a Territory Manager, heading up Malawi, selling Technology, Middleware & Applications across all industries. I’m part of the Transition Cluster Team, a powerful team headed by the seasoned Senior Director. As a Territory Manager my role is to push for coverage, to penetrate the market by selling Oracle from end- to- end to all accounts in Malawi. I now spend my days living out of a suitcase, moving from hotel to hotel, chasing after business in all areas of Malawi. It’s the life of a Sales Man and I’m enjoying every minute of it. I’m truly fortunate and grateful to have been part of such a wonderful graduate program. I owe my Sales career to the graduate program, and I truly hope that the program will continue to develop and to groom new talent amongst the youth of this world. If you're interested in joining the Graduate Program in South Africa keep an eye on our CampusatOracle Facebook Page page to get the latest updates! /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-qformat:yes; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin-top:0in; mso-para-margin-right:0in; mso-para-margin-bottom:10.0pt; mso-para-margin-left:0in; line-height:115%; mso-pagination:widow-orphan; font-size:11.0pt; font-family:"Calibri","sans-serif"; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-fareast-font-family:"Times New Roman"; mso-fareast-theme-font:minor-fareast; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:"Times New Roman"; mso-bidi-theme-font:minor-bidi;}

    Read the article

  • Dual pane file manager for Mac OS

    - by Alex Kaushovik
    Is there a good customizable dual-pane file manager for Mac like Total Commander / Far Manager in Windows, or like Krusader / Midnight Commander in Linux? I used to work on Windows for quite a while and mostly used Far Manager and sometimes Total Commander, then I switched to Ubuntu Linux and used Krusader, now I switched to Mac OS (Snow Leopard) and I'm having a hard time trying to find a good file manager... Many of the existing applications are trying to replace the Finder with "multimedia capabilities nobody cares about in file manager - IMHO" (Path Finder, ForkLift), some of them are almost good dual-pane file managers (couldn't remember examples), but none of them worked for me mostly because of one reason: I couldn't integrate my file/folder comparison utility (Araxis Merge for Mac) with them... The way it worked for me in Windows and Linux is that I was setting the cursor on one file in the left pane, then setting the right-pane cursor on another file in right pane, then I pressed a hotkey that launched Araxis Merge with those to files/folders comparison results. It was very easy to set up in Far Manager (Windows) and Krusader (Linux, actually in Linux I used "Meld" instead of Araxis Merge...) The tool I'm looking for doesn't necessarily has to be free... Thank you!

    Read the article

  • Dual pane file manager for Mac OS

    - by Alex Kaushovik
    Is there a good customizable dual-pane file manager for Mac like Total Commander / Far Manager in Windows, or like Krusader / Midnight Commander in Linux? I used to work on Windows for quite a while and mostly used Far Manager and sometimes Total Commander, then I switched to Ubuntu Linux and used Krusader, now I switched to Mac OS (Snow Leopard) and I'm having a hard time trying to find a good file manager... Many of the existing applications are trying to replace the Finder with "multimedia capabilities nobody cares about in file manager - IMHO" (Path Finder, ForkLift), some of them are almost good dual-pane file managers (couldn't remember examples), but none of them worked for me mostly because of one reason: I couldn't integrate my file/folder comparison utility (Araxis Merge for Mac) with them... The way it worked for me in Windows and Linux is that I was setting the cursor on one file in the left pane, then setting the right-pane cursor on another file in right pane, then I pressed a hotkey that launched Araxis Merge with those to files/folders comparison results. It was very easy to set up in Far Manager (Windows) and Krusader (Linux, actually in Linux I used "Meld" instead of Araxis Merge...) The tool I'm looking for doesn't necessarily has to be free... Thank you!

    Read the article

  • Dual pane file manager for Mac OS X

    - by Alex Kaushovik
    Is there a good customizable dual-pane file manager for Mac like Total Commander / Far Manager in Windows, or like Krusader / Midnight Commander in Linux? I used to work on Windows for quite a while and mostly used Far Manager and sometimes Total Commander, then I switched to Ubuntu Linux and used Krusader, now I switched to Mac OS (Snow Leopard) and I'm having a hard time trying to find a good file manager... Many of the existing applications are trying to replace the Finder with "multimedia capabilities nobody cares about in file manager - IMHO" (Path Finder, ForkLift), some of them are almost good dual-pane file managers (couldn't remember examples), but none of them worked for me mostly because of one reason: I couldn't integrate my file/folder comparison utility (Araxis Merge for Mac) with them... The way it worked for me in Windows and Linux is that I was setting the cursor on one file in the left pane, then setting the right-pane cursor on another file in right pane, then I pressed a hotkey that launched Araxis Merge with those to files/folders comparison results. It was very easy to set up in Far Manager (Windows) and Krusader (Linux, actually in Linux I used "Meld" instead of Araxis Merge...) The tool I'm looking for doesn't necessarily has to be free... Thank you!

    Read the article

  • Monitora&ccedil;&atilde;o com Oracle Enteprrise Manager

    - by fernando.galdino
    A figura abaixo oferece uma visão geral das possibilidades de monitoramento providas pelo Oracle Enterprise Manager (OEM), que é uma ferramenta que permite gerenciar a infraestrutura de TI da empresa. Um componente importante da solução é chanado OEM Grid Control. Esse componente permite gerenciar, visualizar e monitorar diversos elementos a partir de uma mesma console. E que elementos podem ser monitorados? No conceito utilizado pelo OEM, os elementos que podem ser monitorados são chamados de Targets, e esses targets envolvem a monitoração de hosts (Windows, Linux, Solaris), Banco de Dados, Middleware, Aplicações Web, Serviços que podem ser customizados pelo administrador, Sistemas e Grupos de targets, além dos aplicativos Oracle. Cada elemento monitorado é ativado através de packs de gerenciamento. Ou seja, há uma série de packs que podem ser adquiridas conforme a necessidade, para permitir a monitoração a partir do próprio OEM Grid Control. Existem packs de monitoramento especiais para banco de dados Oracle, packs de monitoramento para Tomcat, Jboss, WebLogic, SOA Suite, Identity Management. A lista é bem extensa e darei mais detalhes em um novo post. Mas caso queira visitar, veja: http://download.oracle.com/docs/cd/B16240_01/doc/nav/overview.htm Além das packs de monitoramento, existem também plugins e conectores. Os plugins permitem o gerenciamento de elementos adicionais, tais como dispositivos de rede, servidores, banco de dados de terceiros (DB2, SQL Server), Vmware, etc. Já os conectores permitem a integração com outros softwares, tais como gerenciadores de requisições de helpdesk, de modo a integrar os alertas gerados pela ferramenta e gerar tickets em ferramentas como CA Service Desk, BMC Remedy e outros. A extensão de funcionalidades é realmente bem vasta. Num próximo post irei comentar sobre o Ops Center, um novo componente que surgiu após a aquisição da Sun. Além do Grid Control e do Ops Center, há outros componentes bem interessantes. A figura abaixo ilustra diversas camadas onde o ferramental Oracle pode ser usado para monitoração. Há uma pack que permite gerenciar os níveis de serviços em todas as camadas ilustradas. Dada uma requisição, pode-se decompor os dados de SLA em cada camada. E há também o Real User Monitoring, que trata de medir a experiência com o usuário. Falarei disso num novo post, mas basicamente a ferramenta permite acompanhar todo o tráfego de rede gerado dos usuários finais até os servidores web, e com isso rastrear como cada usuário usa a aplicação, quanto tempo ele navega pelo site, se ele enfrentou algum tipo de problema, se houve algum pedido não finalizado devido a algum problema na infraestrutura. É uma ferramenta bem interessante, falarei um pouco mais dela depois. E claro, há também componentes para a realização de testes funcionais e de carga. Em breve, aqui no blog :)

    Read the article

< Previous Page | 24 25 26 27 28 29 30 31 32 33 34 35  | Next Page >