When to implement: Together with or after the source product?
- by Jeremy Oosthuizen
Somebody recently relayed a prospect's question to me: How hard would it be to implement OUBI after the source product (CC&B, WAM or NMS) has already been implemented? Fact is that MOST non-OUBI Data Warehouse / Business Intelligence implementations take place after the source application(s) are in place and hopefully stable. If an organization decides that they need better reporting and management information, then the logical path (see The Data Warehouse Institute's Data Warehouse Maturity Model) is to a Data Warehouse -- no matter when their last applications were implemented. If there is a pre-built Data Warehouse for their specific application, or even for the desired business process in their industry, they're in luck. Else they have to design and build from scratch, using a toolset. The implementation of a toolset is unlike the implementation of OUBI which, like OBI Apps, contain pre-built ETL routines and user content. Much has been written before about the advantages of that.
So, because OUBI is designed specifically for Oracle Utilities transactional products, we often implement them in parallel -- with OUBI lagging a little behind by necessity, like Reporting. Customers know from the start they're going to need the solution, and therefore purchase the products at the same time.
My biggest argument FOR a parallel installation/implementation of OUBI with the source product is two-fold:
- There could be things (which is the technical term for data elements) that customers figure out they need when implementing OUBI, which are often easier added to the source product's implementation project, than to add later;
- OUBI's ETL often points out errors (severe or not) with converted data, which are easier to fix during the source product's implementation project, or it may even be impossible to fix afterwards. The Conversion routines sometimes miss these errors, because the source system can live with the not-quite-perfect converted data. If the data can't be properly extracted, i.e. the proper Dimensions linked to the Facts, then it can't get into OUBI. That means it can't be analyzed effectively along with the rest of the organization's data.
Then there is also the throw-away-work argument, which may be significant. The operational / transactional system cannot go live without reports on Day 1. A lot of those reports would be taken care of by the implementation of OUBI. If OUBI is implemented after go-live, those reports STILL have to be built during the source product's implementation project, but they become throw-away after the OUBI implementation.
I have sometimes been told that it is better to implement OUBI after the source product, because it cuts down on scope and risk for the source product's implementation project. All I can say to that, is bah humbug. No, seriously, given the arguments above, planning has to include the OUBI implementation and it has to be managed properly -- just like any other implementation. If so, it should not add any risk and it should be included in the scope from the start.
The answer to the prospect's question is therefore that it is not that much more difficult; after all, most DW/BI implemenations are done like that. They just have to consider the points above.